Range Improvements Status

Projects that are complete:

1.  New service for the Club's main electrical panel.

2.  Installed a self closing and locking personnel gate on the Steel Bay - still working on the locking mechanism

3.  Installed a high pressure professional misting system on the Public Range

Projects Still Working to Complete:

1.  Moving the far west 50yd berm on the Public Range to 35yds and placing target positions at 25yds, 10yds and 7yds

2.  Installing Drainage Pipes in the Wash Between the Public & High Power Lots to Get Rid of the Dip.

3.  Placing Particians on the Top of Practical Bays 1 & 2.

4.  Improving the Floor in the Indoor Range.


Thanks and feel free to send any comments or suggestions to Lonnie Roberts at lroberts1@cox.net